Total Pageviews

Thursday 28 May 2015

Handover - 25 May 2015

We have the keys!!! Finally. This week has been hectic to say the least and on top of that we have no internet at the house for another couple of weeks so updated this blog has been difficult.
When I was reading other people's building blogs I became so frustrated that when they got keys the blog finished. I will endeavor to not do that and will update as soon as I can!


Thanks for reading so far :)


Wednesday 13 May 2015

Practical Completion Inspection (PCI) & progress pics

So, today my son & I met Site Supervisor 'S' on site to complete the Practical Completion Inspection. This means that essentially everything is done bar a few little things and a few paint touch ups etc. We were pretty happy with the house and am now looking forward to settlement and finally getting the keys.

To be completed prior to handover:
- minor paint touch ups
- feature wall in living room to be painted
- data points to be installed
- phone point to be installed
- extra powerpoint in garage to be installed
- NBN connection plates to be fit off
- front side window to be replaced (cracked)
- weather seals to be installed (front door)
- air con duct casing in bed 2 to be replaced (broken)
- plug for bath to be provided
- appliances to be installed (on day of settlement)

Progress Pics from today:

INTERNAL:

Laundry

Laundry

WIR Bed 4

Main bathroom shower cubicle

Main bathroom

Main bathroom

Main bathroom

Main bathroom

Main bathroom


Bed 3 & WIR

Bed 3

Bed 2 WIR

Bed 2

Bed 2 & 3

Passage

Linen cupboard

Linen cupboard

Passage




Pantry

Kitchen & door to garage

Kitchen

Kitchen/Dining

Kitchen/Living

Kitchen/Living

Theatre & front hallway


Front hallway

Kitchen

Living

Dining/Living/Kitchen

Dining/Living

Ensuite

Ensuite shower cubicle

Ensuite

Master WIR

Master & ensuite

Master & ensuite

Ensuite

Ensuite & WIR



EXTERNAL: